Steel Crackers has completed installation of an induction furnace in dist. Hooghly, West Bengal

Steel Crackers has completed installation of a 1×4 tonne induction furnace at Village Dhobapukur, dist. Hooghly, West Bengal on 5.615 acres of existing land. The estimated cost of the project is Rs. 15 million. The project has came up in the existing plant comprising of a 2×5 tonne furnace producing 42,000 TPA of billet/ingot & 2000 TPA re-rolled bars. Work on the project was completed in 2015. The project is waiting for Consent To Operate order from the Government. The project is scheduled for commissioning after the receipt of Consent To Operate.

Source : https://www.domexinfo.in/blog/induct...-installation/