after 5 min cutting 85% power
temp. of water is already 35 C
room temp 20 C
is this normal
or is the chiller defect ?
after 5 min cutting 85% power
temp. of water is already 35 C
room temp 20 C
is this normal
or is the chiller defect ?
not normal on mine i can run mine all day and not hit 35 i use automotive antifreeze in my chiller 50/50 mix using distilled water
what are you doing that you need that kinda power all the time?
cutting laminated wood/plywood 6mm
but i wonder if the chiller is not broke.
Might wanna run a industrial chiller or toss a wort chiller inline or make your own wort chiller by twisting copper tubing into length of coil its a simple heat exchange
Just check you chiller settings first.
CNC lasers, constructions, service
checked it twice today.
the black pump for the cooling gas/liquid is very hot
all tubes of copper and th ebig cooling block cold !!!!
water is warm
i get the feeling that there is no R404 or freon or whatever must be in there
if i take a look at a standard fridge ,the cooling block is always hot !
something is wrong here
So call nearest fridge service.
CNC lasers, constructions, service
Would a chiller like this work to cool glycol from 200F (93C) down to 75F (23.8C)? do you know what the GPM or Litres per minute capacity it has? Goal - cool 31 gallons of beer down as quickly as possible. Glycol would be used with a heat exchanger.
CW5000 (similiar to 5200) has about 2400-3000 Btu/h
So you may count what you need.
CNC lasers, constructions, service
its all working now
s&a send new pump and i bought also a new extra chiller
good to know, there are some good reliable chinese producers
Good to see you have a new chiller from China.
we are the S&A chiller manufacturer,
Industrial chiller failure Cause
1.Blocked dust gauze, bad thermolysis; Approach: Unpick and wash the dust gauze regularly
2.Poor ventilation for air outlet and inlet; Approach: To ensure a smooth ventilation for air outlet and inlet
3.Voltage is extremely low or astable; Approach: To improve the power supply circuit or use a voltage regulator
4.Improper parameter settings on thermostat; Approach: To reset controlling parameters or restore factory settings
5.Switch the power frequently; Approach: To ensure there is sufficient time for refrigeration (more than 5 minuets)
6.Excessive heat load; Approach: Reduce the heat load or use other model with larger cooling capacity
S&A company specializes in producing industrial water chillers for more than 12 years , S&A chiller series include:CW-3000,CW-5000,CW-5200,Email: [email protected]