Hi Scott,
Just installed the latest version.
On machine configuration (Lathe), I just noticed there's no Run time estimating dialogue box to configure the rapids + t/c time (as there is in the mill)?
Cheers,
Terry
Hi Scott,
Just installed the latest version.
On machine configuration (Lathe), I just noticed there's no Run time estimating dialogue box to configure the rapids + t/c time (as there is in the mill)?
Cheers,
Terry
Terry,
You don't get the dialog box at all? What happens when you click the menu for run time estimating?
Scott
Hi Scott,
If I generate a report, it gives a rapid rate of 100, with a tool change time of 5 s (defaults?).
Cheers,
Terry
Terry,
There are settings in the Machine Configuration now for the rapid rate and tool change time. These are probably what you are seeing.
Scott