    run time estimation

    I have been doing a lot of estimating recently with more on the way. It seems to me when I use a canned cycle for the lathe such as G76 the time only shows one pass instead of many passes and the time estimate comes up short. Does anyone else find this same situation or is there something else I should be doing?

  2. #2
    Join Date
    Mar 2003
    Posts
    765
    This is a known issue with the lathe run time estimation. Since NCPlot only shows the final profile for the canned cycles the run time is based on just the one pass. Until we get it to display all the roughing motions, the run time will be short.

    Scott

Similar Threads

  1. time estimation
    By camtd in forum FeatureCAM CAD/CAM
    Replies: 3
    Last Post: 04-23-2009, 10:56 AM
  2. Run time estimation
    By barbter in forum NCPlot G-Code editor / backplotter
    Replies: 3
    Last Post: 08-04-2008, 04:54 PM
  3. Time to Buy
    By Gorillakilla in forum Stepper Motors / Drives
    Replies: 3
    Last Post: 06-24-2008, 09:52 PM
  4. milling time (not to be confused with hammer time)
    By barefoot0 in forum G-Code Programing
    Replies: 4
    Last Post: 05-03-2007, 12:18 AM
  5. X2 Conversion Time (shopping time)
    By Micro Rotors in forum Benchtop Machines
    Replies: 2
    Last Post: 03-04-2007, 06:11 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •