potentially dumb question here. I am thinking about moving the business, and I currently have about 20 CNC machines. When I am looking for a building, how do I calculate how much power I need? Is it the kVa that is specified in the manuals, or the Fused Amperage? (For instance, a Hitachi Seiki Hicell 30 says power required is 32Kva, 125A Fused). Also, if the building has 800A service three phase, is it 800A per leg?