Well, after having been let down again by my local fabricator I've actually started on the steel work myself.
Today I made a start on sizing all the structural steel for the sub frame. This is big stuff and very heavy: 250mmx150mm and either 8mm wall or 12mm.
Hopefully tomorrow I will have it all cut up and then I can start on the welding.
Attachment 384782Attachment 384784
Decided to finally get on with this build today.
I started to weld one of the three leg sections together. This is a fair amount of work as the steel is very thick.
I had to install a lifting eye on the bottom cross member just so I could flip the section over for welding.
Attachment 390918Attachment 390920Attachment 390922Attachment 390924Attachment 390926Attachment 390928
Nice welds. But the mag drill is for feeble women folk!
@Matth
If you ever decide to get rid of the 400w servos, hit me up or post them in the classified section. I had just started looking around for servos to upgrade my machine from steppers.
Other than that, nice looking build. Just wish I had the time and money to put into a heavy duty build like this lol.