G59 P?????
So, figured out that work offsets are my ticket on a multi-part fixture I'm working on. Figured it out how to setting it all up... well okay that may be a stretch..... In Fusion 360, I have my OP setups with G55, G56, G57, G58, G59 set (however I have to manually go in post edit and fix the G55-G59 settings - it wants to post out G59 P55, G59 P56 and so on). On the machine I go into the MDI line put in G55 - probe my part for zero, MDI - G56 - probe my part for zero, MDI - G57 - probe my part for zero, MDI - G58 - probe my part for zero, MDI - G59 - probe my part for zero. All good up to this point.
Background: Each OP uses the same tool, however at each WCS there is a different operation being done. In this case I have 8 total operations to complete the part.
So has got me wondering how do I set up for much larger setups? As in this case I have 8 operations. G54 thru G59 gives me WCS for 6 operations. How do I go into probe the part for G59 P7 & P8? If I go into the MDI line and put in G59 P7 I get an error.
Let me know if I've left something off in my explanation.
PathPilot 1.9.7
Fusion 360
Thanks,
Awall
The Body Armor Dude - Andrew