I am running single phase power to my Haas Mini Mill 2. Should I use a 2 pole or 3 pole switch? The mill is about 35 feet from the panel. Panel is in a different room.
I am running single phase power to my Haas Mini Mill 2. Should I use a 2 pole or 3 pole switch? The mill is about 35 feet from the panel. Panel is in a different room.
For NEC/CEC A disconnect separate to the main enclosure is allowed for machines with motors totaling 2HP or less, as long as it is within 20ft of the operator and within sight.
CNC, Mechatronics Integration and Custom Machine Design
“Logic will get you from A to B. Imagination will take you everywhere.”
Albert E.
My new Mini Mill 2 is now installed and making chips. Used #6 wire. I was delayed for a while as I had trouble finding a Federal Pioneer breaker. Really happy with the mill. It is so much faster than my Pulsar or my buddy's Tormach 1100. Thanks to everyone for your help answering my questions.